HUATAO GROUPHUATAO GROUP

How to Specify a Replacement Pressure Screen Basket for an OCC Line

Learn what to include in an OCC pressure screen basket RFQ, from machine identification and basket drawings to fit checks and trial acceptance.

How to Specify a Replacement Pressure Screen Basket for an OCC Line

A replacement pressure screen basket must fit the installed screen and suit the duty of that stage. For testliner mills using old corrugated containers (OCC), a useful request for quotation includes the machine identity, the approved basket drawing and the operating problem that prompted replacement.

ANDRITZ reported on February 13, 2026 that Indah Kiat had started up an OCC stock preparation and reject treatment system at its Karawang mill in Indonesia. The project illustrates the combination of pulping, cleaning, sorting and reject treatment in a testliner furnish system. Source: https://www.andritz.com/newsroom-en/pulp-paper/2026-02-13-indah-kiat-group

Identify the screen and its duty

Record the mill equipment tag, screen manufacturer and model, basket position and the approved drawing revision. Note the pulp stream, screening stage and matching rotor. Take photos of markings and the mounting interface. If you supply a worn sample, label worn areas and use the approved drawing to establish original dimensions.

Describe the furnish and the reason for replacement

Record the OCC furnish, operating consistency and throughput where available. Report whether the mill is replacing a worn basket, investigating plugging or reviewing screening performance. Include the current opening size and type, plus observations such as changes in differential pressure or reject flow. Ask the mill engineer to review any proposed change in opening geometry against the process requirements.

Verify mechanical fit before ordering

Ask the supplier to identify the mounting and sealing interfaces, basket orientation, material, opening specification and dimensional tolerances on a drawing for approval. Confirm the relationship between the basket and the installed rotor, including the relevant clearance check. The mill should verify fit against its approved equipment documentation before authorizing manufacture.

Define inspection and trial acceptance

Agree on the inspection records and measurements required at receipt. For a trial, record the incumbent basket’s condition and comparable operating data, then agree on the readings to monitor after installation. Keep the approved drawing and trial notes with the equipment record so the next purchase starts with verified information.

For a technical quotation, share the equipment tag, approved drawing or marked photographs, current opening specification and the operating issue with HUATAO GROUP.

Sources

Hole Screen Basket Slot Screen Basket Pressure Screen Rotors HUATAO Technical RFQ